| Component of the project | Estimated Cost (Lakh Taka |
|---|---|
| Revenue Component | |
| Outsourcing of Staffs | 65.80 |
| Fuel & Lubricant | 6.00 |
| Preparation & printing of structural design and drawing, architectural drawing, estimate, tender document, DPP etc. | 9.00 |
| Purchase of Stationaries | 6.00 |
| Advertisement | 6.20 |
| Foreign Training/Study Tour | 35.00 |
| Consultancy (including VAT, TAX & other logistic supports) | 39.00 |
| Fee/Remuneration/Honorarium | 17.00 |
| Topography/Digital Survey | 0.50 |
| Hiring Charge for rented vehicle | 16.80 |
| Capital Component | |
| Vehicle Purchase | 80.00 |
| Computer and other accessories | 3.75 |
| Office Equipment | 7.50 |
| Furniture, utensils etc. | 200.70 |
| Arboriculture | 20.00 |
| Site development/Removal of Earth | 183.39 |
| Functional Building (Including internal water supply & electrification, External water supply, boundary wall, site office, guard shade, internal road, drain, apron, rain water harvesting) | 15509.68 |
| Other cost of the building (External Electrification & Foundation stone laying, inauguration of project, digital display, festoon, banners etc.) | 3661.60 |
| Physical Contingency | 198.68 |
| Price Contingency | 198.68 |
|
| 20265.28 |